Construction In Progress
Earthworks and Pipeline Construction (2 Sections) of Geodan Housing Si…
페이지 정보
작성자 BAN SEUK CONSTRUCTION CO., LTD 작성일2022-02-18본문
- Project title: Earthworks and Pipeline Construction (2 Sections) of Geodan Housing Site Construction Segment 3-2
- Construction Period: Construction Period: June 10, 2022 to August 24, 2024
- Main Contractor: HANWHA ENGINEERING & CONSTRUCTION CORP.
- Client: Incheon Regional Headquarters of Korea Land and Housing Corporation
- Overview of Construction: Earthworks, roadworks, waterworks, sewage works, bridge works, etc
Construction Information
[Work scope]
Earthwork : Excavation 2,239,000㎥, Compaction fill 165,000㎥, Disposal 188,000㎥ + 2,479,000㎥